
Reinforced Concrete Frames
Adelphi Wharf, Manchester (Phase 1)
Phase 1 of this project started in April 2016 and completed in May 2017. This £6.25m residential project provided 320 apartments over 3 interlinked blocks.
Using waterproof Concrete in the basement to this riverside project, the contract was delivered on time and on budget, much to the appreciation of the client, Beaumont Morgan Developments Ltd.
Phase 2/3 of this project is now underway with a value to David Ashley Construction Ltd of over £10m and due for completion in May 2018.
Sense Touchbase, Selly Oak
This project for Stepnell Construction Ltd was completed in the summer of 2016 and attached a contract value of £1.4m.
The three storey frame and associated groundworks were carried out by ourselves within programme and is a great example of the high level of finish we can achieve (most of the soffits were exposed).
Wolverhampton University
This Science Technology Building for Clegg Construction Ltd took advantage of our early design input and as a result shaved weeks off the initial construction programme.
Completed in September 16, the building is being considered for numerous awards for both design and workmanship.
De Montford University, Leicester – Balfour Beatty
David Ashley Construction Ltd. supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps. This University learning block was carried out for Balfour Beatty over a 36 week programme. See examples of large raked columns.
- £4.2m Subcontract value
- 36 week programme
- Balfour Beatty Construction Ltd.
- Learning Centre over 6 floors
Byron House, Nottingham Trent University
David Ashley Construction Ltd. supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps. Creating new student accommodation for Nottingham Trent University through Vinci Construction Ltd.
- £1.6m Subcontract Value
- 25 weeks Programme duration
- Completed to Budget and Programme
Charles Street, Sheffield
David Ashley Construction Ltd. supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps. This student union building was for Sheffield Hallam University and provided the typical city centre challenges for movement, cranage and logistics – all of which were overcome through meticulous planning and communication.
- £4.2m Subcontract Value
- Balfour Beatty Construction Ltd.
- 35 week programme
Christchurch Primary School, Burton Upon Trent
David Ashley Construction Ltd. supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps. Comprising of circular columns, walls and slabs.
- Subcontract Value of £50k
- Seddon Construction Ltd.
- 17 week Programme duration
Harrogate Police Station
David Ashley Construction Ltd. supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps.
- £1.6m project
- 35 week subcontract programme
- G.B. Building Solutions Ltd.
South Farm Equestrian Centre, Grimsby for North Midland Construction
DACL supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps.
-
5,000m2 Footprint 5 Levels Private House
-
£3.0 million Subcontract Value
-
40 week Duration
Kirklees College, Huddersfield, Allenbuild Limited
DACL supply concrete, reinforcement, formwork and falsework as well as supply of cranage and pumps.
-
£6.2 million Subcontract Value
-
37 week duration
-
5,000m2 Footprint with 6 Stair and Lift Cores
constructed with Slipform.
Westgate, Wakefield for Clegg Construction Limited
DACL supplied groundworks, drainage, concrete, rebar, falsework and formwork as well as supply of cranage and pumps.
-
4 Storey Concrete Frame with Basement and 3 Ground Floor Blocks
-
£2.1 million Subcontract Value
-
26 week duration
Anchorpoint, Sheffield
DACL supplied groundworks, drainage, concrete, rebar, formwork and falsework as well as supply of cranage and pumps.
-
Block A 800 m2 Footprint with stair and lift core
constructed with Slipform – 5 Levels. -
Block A Tower 400m2 Footprint, 9 Levels
-
Block B 900m2 Footprint, 6 Levels
-
Block C 800m2 Footprint, Levels
-
£4.2 million Subcontract Value
-
32 week duration
Brewery Wharf, Leeds, for Totty Construction
DACL supplied concrete, rebar, formwork and falsework.
-
£3.2 million Subcontract Value
-
Duration split into phases over 2 years.
-
1no 5 Level Block, 2no 6 Level Blocks,
2no 8 Level Blocks and 1no 9 Level Block
Urban Edge, New York Street and Ice Street, Leeds
DACL supplied groundworks, drainage, concrete, rebar, formwork and falsework.
-
2 no 7 Storey Blocks
-
£2.2 million Subcontract Value
-
45 week duration
Origin, Princess Street, Manchester for West Contracting Limited
DACL supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps.
-
3,500m2 Footprint 4 Level Basement Carpark
-
£4.1 million Subcontract Value
-
31 week duration
Rossington All Saints School, Doncaster, for Allen Build Limited
DACL supplied concrete, rebar, formwork and falsework as well as supply of cranage and pumps.
-
School, 2 Levels with Sloping Concrete Roof
– All Exposed Concrete Finish. -
£2.1 million Subcontract Value
-
32 week duration
Lower Broughton, Salford, Manchester for Countryside Properties
DACL supplied drainage, concrete, rebar, formwork and falsework as well as supply of cranage and pumps.
-
2 levels with Carpark above Retail, 2,700m2 Footprint
-
£3.0 million Subcontract Value
-
27 week duration